In slab placement, what comes directly before concrete floating? Select one: a. Formwork placement b. Curing c. Troweling d. Pouring e. Strike-off

Respuesta :

bratislava bratislava
  • 11-02-2020

Answer:

e. Strike-off

Explanation:

  • The precast suspended slabs are considered by pouring the slabs in a framework of the slabs and then lifting the slabs into suspended postilions in the structure.
Answer Link

Otras preguntas

How did the approach taken by the United Farm Workers differ from the approach taken by the National Association for the Advancement of Colored People? The Unit
What is the measure of the missing angle? Triangle with two angles labeled
is the principle "separation of powers" evident in the US Constitution?
What is 8^1/2 in simplest form
Who sang "Purple Haze"?
how many hundreds are in 20 tens? how?
How do I find out the perimeter?
What did King Henry VIII do when he wanted to divorce his wife? a. He gave land to the Church in return for his divorce. b. He convinced Parliament to start a n
In England, people associate the acceptance of their Bill of Rights with the reign of who?
can u pl help me with these question in the pic and show how to wrok them out plzz