It takes one week for a crew of workers to pave 3/5 kilometer of a road. At that rate, how long will it take to pave 1 kilometer?

Respuesta :

ayfat23
ayfat23 ayfat23
  • 12-03-2021

Answer:

1.67 weeks

Step-by-step explanation:

Let X= time it will take to pave 1 kilometer?

1 week=3/5 kilometer

X week =1 kilometer

Cross multiply

3/5 X= 1

3X= 5

X= 5/3

1.67 weeks

Answer Link

Otras preguntas

list 3 important facts about being healthy and fit​
What does the line "But for me it was not over" (line 87) imply about the speaker? A. The speaker lives in the past. B. Happiness is out of reach for the speake
effects of cariolis force​
how do boundaries reflect ideas of territoriality and political power on various scales
What is the pressure, in mmHg, of a 4.00 g sample of O2 gas, which has a temperature of 37.0 °C, and a volume of 4400 mL?
Waterpark Party what is the generalization ​
PLSS I NEED HELP ASAP I WILL GIVE THE BRAINLIEST This poster is political, social, or commercial? and why?
A triangular prism has a base perimeter of 32 cm and a height of 15 cm what is the lateral surface area of the prism A. 240 cm2 B. 432 cm2 C. 160 cm2D. 480 cm2
A rug has an area of 28 square feet and is 4 feet wide. What is the perimiter of the rug?
Which organ is most directly involved in the excretion of waste products? Please help